2 Days! The Shortest Wire Drawing Machine Commissioning Time!


Post time: Jan-20-2023   View: 289

In December 2022, we successfully assisted the customer to finish the commissioning of 17-die medium wire drawing machine in only 2 days.
Generally, it takes about two weeks for the commissioning of a medium wire drawing machine, but there are many reasons why LINT TOP can complete the commissioning work in only 2 days.
1. Before the wire drawing machine leaves the factory, we have carried out corresponding testing and trial operation to ensure that the wire drawing machine can fully meet the customer's needs, which can reduce a lot of commissioning time in the customer's plant.
2. Mr. Berarma, a colleague of the North Africa branch, is an experienced engineer. He helps customers to debug on site. At the same time, domestic engineers also remotely communicate with them about the debugging results and key points before leaving the factory.
On the first day, the customer carried out the wiring work of the electric control cabinet, and then carried out the trial operation of the pay-off and take-up, and then the whole set of equipment was tested under the guidance of LINT TOP engineers. The next day, the customer carried out load debugging.
During 06 hours of work, we successfully commissioning of the medium wire drawing machine in only 2 days, and production of two different diameters 0.85mm and 1.54 mm. The performance of the finished wires fully meets the customer's requirements.
The commissioning of the whole wire drawing machine took only two days, which fully proved the stability of our equipment and the professionalism of our engineers. I am very happy that the final result is satisfactory to both parties.
If you also have needs for wire drawing machines, please contact us, we will provide you with the most professional and prompt service.